Calculate the Complete Quantity of Pipe Support Foundation
Calculate the Complete Quantity of Pipe Support Foundation
calculate the volume of concrete and rebar excavation backfilling etc
footing and pedestal. quantity of backfilling materials. a number of the base plate.
I have some given data
I have one pipe support drawing they have mentioned in all detail.
length of pipe support foundation =2.5m
width of pipe support foundation=1.5m
height of footing =0.500m
Total height of pedestal =1.5m
above ground =0.300m
length of pedestal =0.450m
width of pedestal =0.350m
Now we calculate the excavation of pipe support
total excavation of pipe support foundation = L×W×H
total excavation of pipe support foundation =2×1.5×1.7=5.1m³
this is the exact excavation of the foundation but for working space, we will do 600mm all side extra excavation. and 100mm for lean concrete. so its means the excavation is
total excavation=3.2×2.7×1.8=15.552m³
learn more
How to Calculate the Cutting Length of Rectangle and Circular Stirrups
How To Calculate The Bar Bending Schedule for Lintel Beam
Now lean concrete
lean concrete is all side 100mm extra and the thickness of lean concrete is 100mm
so
lean concrete =2.2×1.7×0.100=0.374m³
Now concrete for the footing
concrete for footing =L×B×H
concrete for footing =2×1.5×0.500=1.5m³
now concrete for pedestal or column
concrere for pedestal or column= L×B×H
concrere for pedestal or column=0.450×0.350×1.5=0.236m³
this concrete is for one pedestal but we have 2 pedestals or columns for pipe support
so total concrete for two pedestals =0.236×2=0.472m³
now we calculate the quantity of rebar for footing
footing rebar
dia of the long bar =12mm
spacing of footing =200mm
dia of short bar=12mm
Now calculate the footing long bar
cutting length of long bar= total length -2(C.C)+2 bends
cutting length of long bar=2000-2(75)+2(19d)=2000-150+2(228)=1394mm=1.394m
Nos of long bar = width of footing/spacing+1
Nos of long bar =1500/200+1=8.5=9bar
total cutting length of long bar =nos of bar×length of one bar
total cutting length of long bar =9×1.394=12.546m
Now
cutting length of short bar=widht of footing-2C.C+2bends
cutting length of short bar=1500-2(75)+2(19d)
cutting length of short bar=1500-150+2(19×12)
cutting length of short bar=1500-150+456=1806mm=1.806m
Nos of short bar =total length/spacing+1
Nos of short bar =2000/200+1=11bar
total cutting length of short bar=nos of bar×length of one bar
total cutting length of short bar=11×1.806=19.866m
Now we calculate the weight of the short and long bars at one time because the dia between the short and long bars is the same so that why.
the total length of long and short bar =length of short of bar+length of the long bar
the total length of long and short bar =12.546+19.866=32.412m
weight of long and short bar =d²/162.25×total length
weight of long and short bar =12²/162.25×32.412=28.766kg=29kg
Now calculate the vertical bar
dia of vertical bar=16mm
height of pedestal or column=1.5m
length of pedestal=450mm
width of pedestal=350mm
cutting length of vertical bar=total height of pipe support foundation-bottom c.c -2dia of the bottom bar -top c.c +bottom bends+top bends
cutting length of vertical bar=2000-75-2(12)-50+(18d)+10d
cutting length of vertical bar=2000-75-24-50+(18×16)+10×16
cutting length of vertical bar=2000-75-24-50+288+160=2.299m
we have 8 nos of the vertical bar
we have 2 pedestals =8×2=16 nos
total cutting length of vertical bar =nos of bar×length of one bar
total cutting length of vertical bar =16×2.299=36.784m
weight of vertical bar=d²/162.25×total length
weight of vertical bar=16²/162.25×36.784=58.038=59kg
now
we calculate the stirrups length and nos of stirrups
we have two types of stirrups one is a rectangle shape and one is a diamond shape
Now 1st rectangle stirrups
Nos of rectangle stirrups =total height of pedestal/spacing+1
Nos of rectangle stirrups =1500/150+1=11nos
we have 2 column=11×2=22nos
cutting length of stirrups=2 sides 350+2 sides 250+2bends
cutting length of stirrups=2(350)+2(250)+2(9d)
cutting length of stirrups=700+500+2(9×10)
cutting length of stirrups=1200+180=1380mm=1.380m
the total length of stirrups =nos of stirrups×length of one stirrup
the total length of stirrups =22×1.380=30.360m
Now calculate the diamond stirrups
no of diamond stirrups=nos of rectangle stirrups
22=22
cutting length of stirrups=4 sides of diamond stirrups +2bends
cutting length of stirrups=4(215)+2(9d)=860+2(9×10)=1.040m
total cutting length of stirrups=nos of stirrups×length of one stirrup
total cutting length of stirrups=22×1.040=22.88m
Now calculate the weight of both stirrups
dia of stirrups =10mm
the total length of stirrups=length of rectangle +length of diamond
total length of both stirrups=30.360+22.08=52.44m
weight of diamond stirrup =d²/162.25×total length
weight of diamond stirrups =10²/162.25×52.44=32.32=33kg
now we calculate the backfilling
backfilling of pipe support foundation up to ground level.
Quantity of backfilling=quantity of total excavation – Quantity of total concrete footing, pedestals, and lean concrete
total concrete=footing and pedestal concrete+lean concrete
total concrete=2.346+0.374=2.720m³
Quantity of backfilling=15.552-2.720=12.832m³
Nos of base plate =2
GET FOR MORE INFORMATION
JOIN US & LIKE OUR OFFICIAL FACEBOOK PAGE
THANKS
3 Comments