How To Calculate The Bar Bending Schedule in Circular Slab
How To Calculate The Bar Bending Schedule in Circular Slab
Calculate the bar bending schedule for circular block the diameter of the block is a pair of 2.5meter
given data,
Learn more
Elements of Road & Carriage Way Details
The main bar is that the diameter of 16mm
The distribution bar is that the diameter of 12mm
Spacing is 200mm and therefore the concrete cowl is 20mm
Solution
Spacing is = 200mm
concrete cowl =20mm
The diameter of the block is =2.5m
Step 01
Calculation of the most bar within the center of the block,
Length of main bar =slab diameter -2(concrete cowl on each sides)
Length of main bar= 2500-2(20)
Length of main bar= 2500-40= 2460mm=2.460m
Step 2
Calculate the nos’ of facet rebar
Number of bar =radius of slab/spacing
Radius =length /2
Radius = 2.460/2=1.230m
Number of bar =radius /spacing
Number of bar = 1.230/0.200= 6.15=7no’s
Now
how to calculate the number of rebar in an exceedingly circular block
Actual variety of 1 sides rebar =Number of main bar – rebar of the middle in block
= 7-1 = 6no’s
Now we discover step by step sides rod
A1=√radius² – spacing² × a pair of
A1= √1.230² – .200² × 2
A1=2.427m
A2 =√radius² –(2×spacing)² × a pair of
A2= √1.230² – 2×.200² x 2
A2=2.3255M
A3= √radius² – 3×spacing² × a pair of
A3 = √1.230² – 3×.200² x 2
A3 =2.147M
A4=√radius² – 4×spacing² × a pair of
A4=√1.230² – 4×.200² x 2
A4= 1.868M
A5= √radius² – 5×spacing² × a pair of
A5=√1.230² – 5×.200² x 2
A5= 1.432M
A6= √radius² – 6×spacing² × a pair of
A6=√1.230² – 6×.200² x 2
A6= 0.540M
We have calculate the worth of
A1= 2.427M
A2= 2.325M
A3= 2.147M
A4=1.868M
A5=1.432M
A6=0.540M
This is one facet length and alternative facet Is same.
A1 TO A6= A7 TO A12
SO NOW
main bar total length is = and all bar A1 TO A12
A1+A2+A3+A4+A5+A6+A7+A8+A9+A10+A11+A12
2.427+2.325+2.147+1.868+1.432+.0.50+2.427+2.325+2.147+1.868+1.432+0.540= 21.478
Total length of main bar= one website +other facet =center bar
Total length of main bar= 10.73+10.73+2.460
Total length of main bar= (23.938)M
NOW distribution bar is additionally a similar length however the diameter is totally different.
Main bar total length =distribution bar total length
23.938=23.938
Now calculate the load of main bar 16mm DIA
Main bar =d2/162×23.938
Main bar weight = 16×16/162×23.938
Main bar weight = in kg 37.828kg =38kg
Distribution bar weight= d2/162×23.938
Distribution bar weight=12×12/162×23.938
Distribution bar weight=21.27kg=22kg